All 48 light pole foundations have been installed. The conduit for the light poles has also been put in.
The decorative concrete for the crossings has been poured on all 4 quadrants. The decorative concrete for the roundabout is 50% finished with expected completion by the end of September.
Sidewalks have been poured on the east side up to 50 ft. from the railroad on both sides. 50% of the sidewalks on the west side have been installed with expected completion by the end of September.
After sidewalks are finished, Kimley-Horn will wrap up coordination of the irrigation installation.
Installation of the railroad conduit is anticipated to begin by mid-October.
The following items will remain pending until the railroad signal conduit is installed:
Railroad signal installation.
Pouring of final 50 ft. of concrete for sidewalks.
Remaining items:
Irrigation.
Landscaping.
Striping.
Final grading.
Area clean-up.
TxDOT expects to install the traffic light by the beginning of December. The completion date of this project is estimated to be in mid-November pending the TxDOT traffic light on Hwy 66.
Plans for this project will remain at 90% until the rest of Gettysburg Blvd. is complete.
Coordination has begun with the Edgewater developer to finalize the project design to 100%.
Project Name
Spent to Date
Estimated Budget
Gettysburg to Blackland
$503,413.62
$2,000,000.00
Project Management & Inspection
With the opening of Water Tower Rd. on July 3, the city will have successfully completed two Bond Projects thus far:
Striping at Memorial Parkway
Water Tower Rd.
The Frontage Road Right Turn Lane project will be done soon with an anticipated completion date of early August.
Woodcreek Blvd. and Riding Club are expected to be completed in the fall of 2023.
Contingency
Due to savings in development agreements paid by Impact Fees Funds and project management and inspection done by city staff, we continue to maintain our 10% contingency.
Cost of Bond Issuance
The City paid about $200,557 as part of the debt sale process.
Project Name
Spent to Date
Estimated Budget
Cost of Issuance
$200,557.40
$150,000.00
Contingency @ 10%
$0
$1,513,730.00
Project Management & Constructions Inspection
$0
$475,318.00
Development Agreements
$0
$978,000.00
Other Road Projects
Other road projects happening within the County that are funded by other means.