Road Bond Projects

Road Bond Projects Map 11.29.2023

Woodcreek Blvd. Extension

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14
  15. 15
  16. 16
  17. 17
  18. 18
  19. 19

Woodcreek Blvd. 

  • Striping has been 100% completed.
  • Oncor finalized the conduit and installed the meter for the railroad signals.
  • The meter, valve, and boxes were installed for the irrigation.
  • Railroad signals are 90% installed. Expected completion date - December 1, 2023.
  • Signs are 80% installed. Expected completion date - November 29, 2023.
  • Irrigation is 60% installed.  Expected completion date - December 5, 2023.
  • Sidewalks are 85% poured. Expected completion date - December 8, 2023.
  • Remaining items:
    • Landscaping. Crews are expected to begin next week and are hoping to finish by December 15, 2023
    • Streetlights. We are working to have crews install these by December 15, 2023.
  • The walkthrough inspection is scheduled for December 18, 2023.
  • TxDOT expects to have the traffic light installed and working by December 22, 2023. 
Project Name Spent to Date Estimated Budget
Woodcreek Blvd Extension $4,673,819.94 $5,236,165.00

Gettysburg to Blackland

  1. 1
  2. 2
  3. 3

Gettysburg to Blackland 

  • Kimley-Horn has sent the 90% set of plans to LJA with the quantities included.
  • City staff made comments on the last set of plans. Kimley-Horn is working on identifying these comments.
  • LJA is working on combining the plan sets and submitting them for review. This process should take approximately 2-3 months.  
Project Name Spent to Date Estimated Budget
Gettysburg to Blackland $563,490.70 $2,000,000.00

Riding Club East/Railroad Crossing

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6

Riding Club (COMPLETED) 

  • Processing final payment. 
Project Name Spent to Date Estimated Budget
Riding Club East/Railroad Crossing $1,190,259.21 $1,524,2400.00

Turn lanes at I-30 & FM 551

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9

Turn Lanes at FM 551/IH30 (COMPLETED)

  • Phase I Memorial Parkway Striping Project (COMPLETED)
  • Frontage Road RTL Extension (COMPLETED)
Project Name Spent to Date Estimated Budget
Turn lanes at I-30 & FM 551 $761,213.92 $1,500,000.00

Water Tower Road North/South

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10

Water Tower RD Extension (COMPLETED)

Project Name Spent to Date Estimated Budget
Water Tower Road North/South  $1,600,000.00 $1,622,547.00

Project Management 

  • As the remaining road bond projects are finalized, the project management team will continue to utilize this page to provide updates on upcoming city projects.

Contingency

  • Due to savings in development agreements paid by Impact Fees Funds and project management and inspection done by city staff, we continue to maintain our 10% contingency.

Cost of Bond Issuance 

  • The City paid about $200,557 as part of the debt sale process.
Project Name Spent to Date Estimated Budget
Cost of Issuance $200,557.40 $150,000.00
Contingency @ 10% $0 $1,513,730.00
Project Management & Constructions Inspection $0 $475,318.00
Development Agreements $0 $978,000.00

Other Road Projects

Other road projects happening within the County that are funded by other means.