Road Bond Projects

Road Bond Projects updated Map 8.30.2023

Woodcreek Blvd. Extension

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14
  15. 15
  16. 16
  17. 17
  18. 18

Woodcreek Blvd. 

  • All 48 light pole foundations have been installed. The conduit for the light poles has also been put in. 
  • The decorative concrete for the crossings has been poured on all 4 quadrants. The decorative concrete for the roundabout is 50% finished with expected completion by the end of September. 
  • Sidewalks have been poured on the east side up to 50 ft. from the railroad on both sides. 50% of the sidewalks on the west side have been installed with expected completion by the end of September.
  • After sidewalks are finished, Kimley-Horn will wrap up coordination of the irrigation installation. 
  • Installation of the railroad conduit is anticipated to begin by mid-October. 
  • The following items will remain pending until the railroad signal conduit is installed:
    • Railroad signal installation.
    • Pouring of final 50 ft. of concrete for sidewalks. 
  • Remaining items:
    • Irrigation.
    • Landscaping.
    • Striping.
    • Final grading.
    • Area clean-up.
  • TxDOT expects to install the traffic light by the beginning of December. The completion date of this project is estimated to be in mid-November pending the TxDOT traffic light on Hwy 66.
Project Name Spent to Date Estimated Budget
Woodcreek Blvd Extension $4,589,469.09 $5,236,165.00

Turn lanes at I-30 & FM 551

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9

Turn Lanes at FM 551/IH30

            Phase I Memorial Parkway Striping Project (COMPLETE)

  • This project has been completed. 

Frontage Road RTL Extension (COMPLETE)

  • This project has been completed. 
Project Name Spent to Date Estimated Budget
Turn lanes at I-30 & FM 551 $760,847.82 $1,500,000.00

Water Tower Road North/South

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10

Water Tower RD Extension (COMPLETE)

    • This project has been completed.
    • The developer reimbursement is currently being processed.
Project Name Spent to Date Estimated Budget
Water Tower Road North/South  $0 $1,622,547.00

Riding Club East/Railroad Crossing

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5

Riding Club  

  • Remaining items: 
    • AT&T will adjust the manhole on the south lane by the end of September.
    • AT&T has relocated the fiber lines for the final Reinforced Concrete Pipeline to be installed. 
    • Paving at the manhole location.
    • Paving of the driveway to Ben Payne Rd. after utilities are relocated.
    • Establish vegetation.
  • The completion date is estimated to be approximately 3 weeks from when AT&T has accomplished moving utilities. 
Project Name Spent to Date Estimated Budget
Riding Club East/Railroad Crossing $1,221,706.76 $1,524,2400.00

Gettysburg to Blackland

  1. 1
  2. 2
  3. 3

Gettysburg to Blackland 

  • Demolition of the existing house is underway.
  • Plans for this project will remain at 90% until the rest of Gettysburg Blvd. is complete. 
  • Coordination has begun with the Edgewater developer to finalize the project design to 100%.
Project Name Spent to Date Estimated Budget
Gettysburg to Blackland $503,413.62 $2,000,000.00

Project Management & Inspection 

  • With the opening of Water Tower Rd. on July 3, the city will have successfully completed two Bond Projects thus far:
    • Striping at Memorial Parkway
    • Water Tower Rd.
  • The Frontage Road Right Turn Lane project will be done soon with an anticipated completion date of early August. 
  • Woodcreek Blvd. and Riding Club are expected to be completed in the fall of 2023.

Contingency

  • Due to savings in development agreements paid by Impact Fees Funds and project management and inspection done by city staff, we continue to maintain our 10% contingency.

Cost of Bond Issuance 

  • The City paid about $200,557 as part of the debt sale process.
Project Name Spent to Date Estimated Budget
Cost of Issuance $200,557.40 $150,000.00
Contingency @ 10% $0 $1,513,730.00
Project Management & Constructions Inspection $0 $475,318.00
Development Agreements $0 $978,000.00